How to apply

This is a two stage process: the application stage, and the reimbursement stage.
 

Stage 1: Application

Applicants who are interested in the scheme must first submit an application form. This should be before works begin to ensure that green roof and vertical greenery proposals qualify for funding.

After application approval, installation can begin and funds will be reserved for 6 months.


Stage 2: Reimbursement

After installation is complete, a reimbursement form must be submitted to receive funding.

 

Further details

There are separate forms for vertical greenery and green roof installations. If a project has both components, forms should be submitted together and may share supporting documents.

Forms can be submitted by either email or post to the address below. Supporting documents may be submitted separately, either by email or post.